Toolings
Maintainer: Matthias Saimpert
🧭 Overview
The last dedicated quad assembly meeting is available here:
👉 Indico Event #1599920
This section gathers details about recent and on-going orders of production tools for the Outer Barrel Wirebond Protection (OBWBP) assembly. It includes links to follow-up the most recent orders, timelines, and assembly instructions.
There are two kind of toolings:
- Pre-production tooling
- Designed and procured at CERN
- 1 tool per OB site → 1 OBWBP assembly per day per site
- OK to assemble production modules
- Production tooling
- Iteration from pre-production design, done at CERN
- Provide enough tools to match the final production rate (≥4 per site)
- Single-module EDMS 3252568/1 and single-cell EDMS 3252569/1 versions
- Pre-production stencil not compatible; single-cell files AT2IPOM_0095 and 0097 missing on EDMS (follow-up in progress)
🔄 Production Tooling Orders
🛠 1st Order – Design Validation (14 single-module + 2 single-cell tools) ✅ Completed
- Machining: company, followed by Diego
- Stencil: company, followed by Matthias/Milou
EDH DAI - Commercial parts (screws, etc.): followed by Wolfgang
- Metrology: EP-EN (CERN), followed by Diego
- Assembly: LPNHE, Siegen, CERN, followed by Matthias/Milou
- OBWBP tooling assembly instructions
- 6 tools assembled by LPNHE, 6 by Siegen, 4 by CERN (2 modules + 2 cell-loaded), CERN will record assembly video
🛠 2nd Order – Final Production (50 single-module + 5 single-cell tools) 🟡 In Progress
- Machining: 3 companies identified, quotes requested, followed by Julien/Diego/Wolfgang
- Some part quantities may change (SR holder, SR insert)
- Separate quotes for machining + metrology and machining alone
- Stencil & Commercial parts: orders mostly passed, followed by Wolfgang
- Metrology: EP-EN (CERN) or company, should include some of the smaller parts as well this time
- Assembly: LPNHE, Siegen, CERN → other volunteer?
🕐 Timeline (Optimistic)
- 2nd order machined parts done: Dec 2025
- Parts for first 7 toolings ready: Feb 2026
- All parts passed metrology and assembled: May 2026
- All tools distributed to sites: June 2026
📌 Executive Summary of Feedback (from Quad Assembly Meeting 28/10/2025)
- General Feedback
- Minor issues with 3D-printed frames and SR holder handling
- Pre-production stencil not recommended; must use production stencil
-
Assembly rates expected to increase gradually:
- Current: 1 tool/day/site
- ~1 month: 2 tools/day/site
- From March: 3 tools/day/site
- From June: nominal rates (site-dependent)
-
Site-specific Notes
- Bonn: 1 production tool validated, 2nd production tool validation pending; do not use SR holder pencil
- Siegen: 6 production tools assembled; 2 sent to Bonn, 2 to Goettingen; SR area insert and frame issues
- Goettingen: 1 production tool validated, 2nd pending; 3D printed frame issues
- IRFU: No tool fully validated yet; machining issues on SR area insert identified
- LPNHE: 2 production tools validated; used pre-production stencil in some cases
- IJCLAB: 2 tools validated; 3D printed frame issues; used pre-production stencil
📝 Ongoing Actions
- Confirm incompatibility between pre-production and production stencils (Manabu / Diego)
- Ensure smaller parts (stencil holder, SR holder) go through metrology for 2nd order
- Verify remaining inventory of commercial parts at CERN (Milou)
- Monitor AngstPfister orders and take necessary actions (Wolfgang)
- Clarify 3D printed frame origin and usage of SR holder pencil
- Consider ordering additional SR area inserts if needed
🔗 Related Resources
- 📄 EDMS – Single-module tools 3252568/1
- 📄 EDMS – Single-cell tools 3252569/1
- 📄 OBWBP Tooling Assembly Instructions (Google Doc)
- 📄 Last status report on Indico (previous was Indico Event #1572095)
- 📄 CERN Procurement Rules
Last update:
2025-10-31